Nashville International Airport > Business Opportunities > Opportunities > RUNWAY SAFETY AREA AND RUNWAY EXTENSION (PHASE 2) CIP 1491A (Closed 7/24/14)

RUNWAY SAFETY AREA AND RUNWAY EXTENSION (PHASE 2) CIP 1491A (Closed 7/24/14)

RUNWAY SAFETY AREA AND RUNWAY EXTENSION (PHASE 2) CIP 1491A (Closed 7/24/14)

(due 7/24/2014)

​This solicitation is now closed.

 

The following bids were received:

 

Civil Constructors, Inc:

Schedule 1 - $8,076,375.00

Schedule 2 - no bid

Alternate 1 - $956,420.00

 

HMA Contractors:

Schedule 1 - $8,407,272.50

Schedule 2 - no bid

Alternate 1 - $835,651.50

 

LoJac Enterprises:

Schedule 1 - $9,236,676.50

Schedule 2 - no bid

Alternate 1 - $1,340,545.00

 

R C Construction:

Schedule 1 - $8,977,006.00

Schedule 2 - $8,960,613.00

Alternate 1 - $1,621,745.00

 

The information listed above in no way guarantees any award.
All bids are subject to evaluation and analysis before an official award is made.
 
Updated information will be posted here as it becomes available.
 

Updated:  7/24/14